Question 179
Main Page
A team deploys a critical system with known risks. What should follow?
A. Fire the project manager
B. Accept the risk silently
C. Document the decision in the risk register with mitigation actions
D. Rebuild the system immediately
Answer: Document the decision in the risk register with mitigation actions
Risk-based decisions must be documented and monitored to manage impact over time.